NEW QUESTION # 44
Test automation is typically included in the Definition of Done (DoD).
- A. True
- B. False
Answer: B
NEW QUESTION # 45
Team A has decided to use the IP Iteration to continue the finalizing Feature delivery work they have been working on for the past two IP Iterations. What is one effect Team A might experience by continuing to stay heads-down rather than using the IP Iteration as intended?
- A. They could lose an opportunity to collaborate with other developers and understand dependencies
- B. They could lose an opportunity to build relationships across the teams
- C. They could lose an opportunity to manage risks and communication within the ART
- D. They could lose an opportunity to consider new approaches to Solution delivery
Answer: D
Explanation:
The Innovation and Planning (IP) Iteration is designed to give teams space for innovation, exploration, learning, and improvement, not for continuing regular feature work. When a team misuses the IP Iteration to "catch up" on delivery, it misses the opportunity to experiment, innovate, and explore new ways to deliver solutions more effectively.
This reduces the long-term adaptability and creativity of the team, limiting their ability to introduce process or technical improvements that could increase efficiency in future PIs. The IP Iteration is also a time for the Inspect and Adapt event and PI Planning, both of which are critical to continuous improvement.
From SAFe guidance:
"The IP Iteration provides dedicated time for innovation and planning. Using it for normal work diminishes opportunities to innovate, learn, and explore new approaches." Therefore, the correct answer is D. They could lose an opportunity to consider new approaches to Solution delivery.
NEW QUESTION # 46
What is one purpose of Iteration Goals?
- A. To identify what to present in System Demo
- B. To align team members to common objectives
- C. To communicate which Stories will be completed during the Iteration
- D. To get feedback from the organization
Answer: B
Explanation:
One purpose of iteration goals is to align team members to a common purpose and vision. Iteration goals are a high-level summary of the business and technical goals that an Agile Team agrees to accomplish in an iteration. They help the team and the product owner to reach agreement on the business value they intend to deliver, align their work to their team PI objectives, and ground everyone on their shared purpose. Iteration goals also provide transparency and management information, as well as support the coordination and dependency management of the Agile Release Train (ART).
Reference:
Iteration Goals - Scaled Agile Framework
Exam Study Guide: SSM (6.0) - SAFe Scrum Master
NEW QUESTION # 47
What description best represents Capabilities as defined in SAFe?
- A. Capabilities are simply a level or abstraction above Features, exhibiting largely the same characteristics and practices.
- B. Capabilities are simply a different kind of Epic, exhibiting largely the same characteristics and practices.
- C. Capabilities are simply a level of abstraction above Epics, exhibiting largely the same characteristics and practices.
- D. Capability is a different name for Features, one that is preferred by some organizations.
Answer: A
NEW QUESTION # 48
What would you examine when identifying Value Streams in an enterprise moving to SAFe?(Select 2)
- A. The number of ARTs which would be contained in the Portfolio.
- B. The current products which the company sells.
- C. The internal departments which are supported.
- D. The project cost accounting procedures in place.
Answer: B,C
NEW QUESTION # 49
What are two common PI planning anti-patterns?
- A. Team decides which changes need to happen and when
- B. Stories are created for the PI planning iterations
- C. Too much time spent analyzing each story
- D. Part-time scrum masters do not have time to plan as part of the team
- E. Too much time spent prioritizing features
Answer: C,D
NEW QUESTION # 50
(Select 2) When might Feature size not be a good substitute for the duration of WSJF?
- A. The Feature did not originate from a Program Epic.
- B. The Feature involves a remote third-party vendor that has a formal scope-approval process.
- C. The Feature did not originate from a Value Stream Capability
- D. The Feature involves a team or team members who represent a bottleneck.
- E. The Feature has not yet been broken down into user stories by the Product Owne
Answer: B,D
NEW QUESTION # 51
What are two good scrum master facilitation practices?
- A. allow for deep meaningful conversations even if it is outside the scope of the agenda
- B. llow unproductive conflict to encourage open communication
- C. create an environment of safety so that everyone feels comfortable contributing to the discussion
- D. ensure all voices are heard
- E. do not enforce accountability as it creates an environment of distrust
Answer: C,D
NEW QUESTION # 52
Individual Team PI performance reports are rolled up into the:
- A. Program Metrics
- B. Program Increment Results Ratio
- C. Program Predictability Report
- D. Program Increment Tally
Answer: C
NEW QUESTION # 53
What is one aspect of the Scrum Master/Team Coach role as it relates to PI Planning?
- A. Briefing the team before planning
- B. Facilitate Coach Sync
- C. Participate in management review and problem-solving
- D. Perform the ART confidence vote
Answer: C
Explanation:
During PI Planning, the Scrum Master/Team Coach (SM/TC) plays an important facilitative and support role. One key responsibility is to participate in the management review and problem-solving meeting that occurs midway through PI Planning.
This meeting allows leaders and Scrum Masters to review the teams' progress, resolve cross-team risks, address scope challenges, and ensure alignment before finalizing PI objectives. The Scrum Master's insights into team capacity, dependencies, and risks are crucial for ART-level decision-making.
From SAFe guidance:
"Scrum Masters participate in the management review and problem-solving session during PI Planning to help resolve issues that may prevent teams from meeting their objectives." Therefore, the correct answer is B. Participate in management review and problem-solving.
NEW QUESTION # 54
What type of anti-pattern is below: "The Agile Team has more than one Product Owner."
- A. Please note down your answer
Answer: A
Explanation:
Explanation/Reference:
A Structural Anti-Pattern
NEW QUESTION # 55
Why is it important to organize the work for Iteration Planning?
- A. So the backlog can be prepared
- B. So the Scrum Master can prepare workload for the Continuous Delivery Pipeline
- C. So the team can load balance
- D. So a realistic work scope can be defined
Answer: D
NEW QUESTION # 56
The three pillars of Scrum are transparency, inspection, and what else?
- A. Collaboration
- B. Self organization
- C. Respect
- D. Adaptation
Answer: D
NEW QUESTION # 57
Team A wants to use the IP Iteration to continue their "usual work." What is one benefit the Scrum Master/Team Coach could share with the team about using the IP Iteration as intended?
- A. The team can do team building activities
- B. The team can prepare for PI planning
- C. The team can take time for personal appointments
- D. The team can allocate time for vacation
Answer: B
Explanation:
The Innovation and Planning (IP) Iteration in SAFe serves a critical purpose-it provides time for innovation, learning, improvement, and preparation for the next Program Increment (PI).
When teams attempt to use the IP Iteration to continue their standard work, they lose the opportunity to rest, reflect, and prepare effectively for future planning. One of the key intended uses of the IP Iteration is to prepare for PI Planning, which includes reviewing objectives, refining backlogs, and ensuring readiness for upcoming work.
From SAFe guidance:
"The IP Iteration provides teams with the opportunity to innovate, improve, and prepare for the upcoming PI Planning event." Therefore, the correct answer is D. The team can prepare for PI planning, as this aligns with one of the primary goals of the IP Iteration.
NEW QUESTION # 58
Which statement is true about the phase-gate milestone model and risk reduction?
- A. It does not mitigate risk as intended
- B. It creates large batches of requirements
- C. It reduces product increment values
- D. It helps to visualize and limit WIP
Answer: A
Explanation:
Explanation/Reference:
https://www.scaledagileframework.com/base-milestones-on-objective-evaluation-of-working-systems/
NEW QUESTION # 59
......