NEW QUESTION # 19
(Select 4) What are legitimate examples of management as an enabling function, rather than as top-down
control?
- A. Developing skills and career paths for team members.
- B. Assigning team members to handle external dependencies.
- C. Creating an environment of mutual influence.
- D. Creating work breakdown structures.
- E. Communicating the Solution Vision with the teams.
- F. Working with other departments to establish better communication among teams.
- G. Assigning backlog items to team members.
Answer: A,C,D,F
NEW QUESTION # 20
Leader as expert and leader as conductor can be appropriate leadership models.
- A. True
- B. False
Answer: B
NEW QUESTION # 21
Understanding the full Value Stream allows you to focus on the delays.
- A. False
- B. True
Answer: B
NEW QUESTION # 22
A Program Epic requires budgetary approval and a lightweight business case only if it spans multiple PIs.
- A. True
- B. False
Answer: B
NEW QUESTION # 23
What description best represents Capabilities as defined in SAFe?
- A. Capability is a different name for Features, one that is preferred by some organizations.
- B. Capabilities are simply a different kind of Epic, exhibiting largely the same characteristics and practices.
- C. Capabilities are simply a level of abstraction above Epics, exhibiting largely the same characteristics and
practices. - D. Capabilities are simply a level or abstraction above Features, exhibiting largely the same characteristics and practices.
Answer: D
NEW QUESTION # 24
In SAFe, who owns the Vision for a PI?
- A. Product Management
- B. Product Owner
- C. Scrum Master
- D. Business Owners
- E. COE
Answer: D
NEW QUESTION # 25
What is the most effective way to train the System Team members to operate effectively as part of the train?
- A. Have them attend SAFe for Teams training with all other teams on the train.
- B. Have them attend Leading SAFe training.
- C. Have them attend Implementing SAFe training with SPC certification.
- D. Have them attend Leading SAFe training and Scrum Master orientation.
- E. Have them review the SAFe Foundations presentation and provide on-the-job training.
Answer: A
NEW QUESTION # 26
(Select 2) What steps in the Portfolio Kanban are most appropriate for running research spikes?
- A. Implementing-teams perform spikes as usual
- B. Portfolio Backlog-run a spike before pulling into development.
- C. Analysis-spikes help clarify feasibility.
- D. Funnel-understand whether the Epic makes sense.
Answer: C,D
NEW QUESTION # 27
A Scrum Master asked you to help her use systems thinking to identify the backlog items that would improve
the system as a whole. Select one item that uses systems thinking most effectively.
- A. Review the burn-down chart at each retrospective to improve team estimating.
- B. Involve representatives of department teams in Iteration Planning and Demos.
- C. Increase unit test coverage.
- D. Make daily stand-ups more engaging and strictly timeboxed.
Answer: D
NEW QUESTION # 28
(Select 3) Which of the following have acceptance criteria?
- A. Program Epics
- B. Enabler Features
- C. Business Capabilities
- D. Spikes
- E. Strategic Themes
- F. Portfolio Enabler Epics
Answer: B,C,D
NEW QUESTION # 29
What is the primary purpose of the management meeting at the end of Day 1 of PI Planning?
- A. To design the next generation of the product.
- B. To evaluate the performance of teams.
- C. To make adjustments to the PI scope and address program challenges.
- D. To assign business value to the teams' draft PI Objectives.
Answer: C
NEW QUESTION # 30
(Select 3) What are the primary reasons to limit WIP?
- A. Increase throughput
- B. Make it easier to visualize the important work
- C. Reduce multiplexing
- D. Expand context switching
- E. Decrease wait times
Answer: A,C,E
NEW QUESTION # 31
What statement applies to Iteration Planning in SAFe?
- A. Teams that have no dependencies may choose not to do Iteration Planning once they have planned the
PI. - B. When the teams define acceptance criteria during PI Planning, Iteration Planning is not strictly required during the PI.
- C. Iteration Planning is required in every Iteration to enable fast learning cycles.
- D. Iteration Planning is required for all Iterations except for the first one, since there's nothing to cause a
change in the PI plan yet. - E. Component teams require Iteration Planning in every Iteration, while Feature teams may or may not,
based on dependencies.
Answer: C
NEW QUESTION # 32
(Select 2) What are the responsibilities of a Business Owner?
- A. Determine the product Roadmap
- B. Assign business value to Team Objectives during PI Planning.
- C. Ensure that the Solution Demo occurs.
- D. Participate in Post-PI Planning and assist trains in adjusting ART PI plans as needed.
- E. Assign business value to Epics and Features.
Answer: B,D
NEW QUESTION # 33
(Select 2) SAFe teams using Kanban are required to participate in which events?
- A. PI Planning
- B. Iteration Retrospective
- C. System Demo
- D. Iteration Planning
Answer: A,C
NEW QUESTION # 34
Where are Capabilities managed?
- A. In the Value Stream Kanban.
- B. In the Value Stream planning board.
- C. In the ART Kanban.
- D. In the Portfolio Kanban.
Answer: A
NEW QUESTION # 35
Backlog items in an Expedite class of service can break WIP limits.
- A. False
- B. True
Answer: B
NEW QUESTION # 36
What should a Supplier using a traditional methodology do when working with ARTs in a Value Stream?
- A. Develop her own Vision and Roadmap.
- B. Demonstrate working software at each Solution Demo.
- C. Attend key Value Stream events.
Answer: B
NEW QUESTION # 37
How does a team calculate its initial velocity during its first PI Planning meeting when teams don't have
historic data?
- A. Assign 10 points per team member (not counting the Scrum Master and Product Owner) and subtract 1point for each holiday or vacation day.
- B. Allow teams to establish their own velocity and then roll them up to calculate the velocity of the train.
- C. Assign 8 points per team member (not counting the Scrum Master and Product Owner) and subtract 1
point for each holiday or vacation day. - D. It is not recommended to calculate velocity until the team has completed its first PI.
Answer: C
NEW QUESTION # 38
Enablers can build or enhance development infrastructure.
- A. False
- B. True
Answer: B
NEW QUESTION # 39
......